SRGUG BUILDING PROJECT

HOME

OFFICERS

MEETINGS

CONSTITUTION

BYELAWS

DIRECTIONS

FACILITIES

HISTORY

GALLERY

Rugby Club Link

Cricket Club Link

Brewery Link

 

21 Dec 07 Bert Higgs of AE Higgs Builders hands over the Clubhouse Keys to the SRGUG Chairman Photo

13 Sept 07 Stanford Rec. car park is re-lined Photos and info

02 June 07 Back patio is laid Photos

22 May 07 Outside work continues / Phase 3 – extra security for the tennis courts – tennis screens are up. Photos

20 May 07 Official opening ceremony Photos and info

17 May 07 Front patio laid / Furniture arrives / 1st floor work photos

13 May 07 Clubhouse cleared for the carpet to be laid & loft insulated/Phase 2 - Benches in dressing room & showers in dressing room 6 photos

04 May 07 Phase 1 – Back bar is installed / Outside work begins behind the new Clubhouse Photos

27 April 07 The New SRGUG facilities open!

22 April 07 Phase 1 – Scoreboard construction is finished - Bar installed / Phase Three - Tennis courts are finished! Photos and info

12 April 07 Phase 1 – Walls painted, more work on the floor, stairs walled in to 1 st floor, further work on the scoreboard / Phase Two – Picture window has gone! Photos and info

31 Mar 07 Phase 1 - Ceiling painted, windows and doors in / Upstairs work has started on the cricket scoreboard Photos

23 Mar 07 Phase 1 - Shutters on scorebox, Ceiling and walls ready for decorating / New Shutters and windows for Phase 2 Photos

16 Mar 07 Phase 1 Ceiling plastered, stairs put in place, Middle Section offers great views / New Fascia for Phase 2 / Phase 3 Tennis Courts ready for colour spraying Photos

09 Mar 07 Work starts on Bar & Kitchen area in Phase 1 / More painting in Phase 2 / Phase 3 – The Tennis Court fence is finished Photos and info

02 Mar 07 The shutters arrive for Phase 1 & 2 / More work on the 1st Floor / The dressing rooms are painted in Phase 2 Photos

23 Feb 07 Phase 1 - Cladding on 1 st Floor / Phase 2 – Roof repairs / Phase 3 - Tarmac is finished on the Tennis courts! Photos and info

19 Feb 07 Tarmac started to be laid on the Tennis courts! Photo

16 Feb 07 Framework of Middle section virtually complete / Plastering begins in Phase 2 / Tennis courts fencing virtually complete Photos

09 Feb 07 More walls on Middle section / Finishing Blockwork / Winter weather does not stop the fence going up! Photos

07 Feb 07 Middle Section of Phase One takes shape / More blockwork + The tennis courts fence posts are up! Photos

02 Feb 07 Preparations for 1 st Floor / Electrics & blockwork in Phase Two / Tennis courts ready for the fence Photos

26 Jan 07 Roof just about finished in Phase One / New walls in Phase Two / More groundwork on tennis courts Photos

18 Jan 07 Updates on all three Phases! Photos

16 Jan 07 Phase three begins (refurbishment of the tennis courts) / The roof on Phase One is halfway there Photos and Info

11 Jan 07 Phase two well underway – more demolition Photos

07 Jan 07 Walls come tumbling down / SLHCC Clubhouse closes Photos and info

21 Dec 06 The trusses are up and are covered Photos and info

19 Dec 06 The trusses arrived Photos & info

12 Dec 06 Further progress as Christmas approached Photos

01 Dec 06 The scaffolding goes up Photos

23 Nov 06 The building starts to take shape Photos

19 Nov 06 The groundwork is virtually complete and the brickies move in Photos

06 Nov 06 More brickwork Photos

27 Oct 06 First bricks laid Photos

13 Oct 06 Footings are dug for Phase One Photos

10 Oct 06 Building work commences Photos

08 Oct 06 Cory Trust agreement signed Photos & info

05 Oct 06 Demolition of the Tea hut Photos & info